Fast turnaround on a tight program
An amenities block package of 164 members, about seven tonnes, on a program with no slack in it. Detailing is usually what sets the pace, because shop drawings have to go through approval and review while the workshop waits. Drawings were done in three days, material was ordered off the approved assemblies before the full construction issue, and the workshop was cutting nine days after kick-off. Five variations came up during approval, each raised with the builder the morning it appeared, and none of them stopped the program.